462 storage projects totaling 7,614 MW are being processed in Spain
Last week, Valladolid hosted AEPIBAL Day 2025, the annual meeting organized by the Spanish association for battery energy storage, AEPIBAL.
In one of the presentations, a spokesperson for Red Eléctrica (REE) stated that there are currently 21 GW of hybridization projects with permits (although she added that a large portion will not be implemented), 11 GW of stand-alone storage, and 340 GW in the commissioning queue.
However, according to data collected by the official bulletins of all provinces, as well as the Official State Gazette (BOE) , at this time a total of 462 projects have started their administrative processing, adding up to 7,614 MW of power in Spain.
Of the total, 47% are hybrid installations with renewable generation and 53% are stand-alone projects. The average power output of the projects is 18 MW and the average capacity is 3.2 hours.